Flowstation Piping Refurbishment
Sectional replacement and refurbishment of corroded flowstation piping, including spool fabrication, installation, hydro testing and reinstatement.
Client
Indigenous E&P Operator
Location
Rivers State, Nigeria
Duration
5 months
Completion
2024
Scope of work
- Corrosion survey support
- Sectional pipe replacement
- Spool fabrication
- Hydro testing
- Coating and reinstatement
Challenges
- Extensive corrosion discovered beyond the original scope
- Limited laydown and fabrication space on site
- Production deferment pressure
Our solutions
- Rapid re-estimation and transparent variation management
- Off-site spool fabrication with just-in-time delivery
- Phased isolation to keep partial production online
Results
- Extended scope absorbed without schedule overrun
- Production deferment minimised through phased execution
- Asset integrity restored with documented test records