Fabrication

Storage Tank Fabrication & Installation

Fabrication, installation, alignment and testing of storage tanks, delivered from our Port Harcourt fabrication capability through to site commissioning.

Client

Aiteo Eastern E&P Company Limited

Location

Rivers State, Nigeria

Duration

6 months

Completion

2022

Scope of work

  • Tank fabrication
  • Installation and alignment
  • Welding and NDT
  • Coating and painting
  • Testing and commissioning

Challenges

  • Tight dimensional tolerances on shell and floor plates
  • Coordination of heavy lifts on a congested site
  • Weather disruption during the rainy season

Our solutions

  • Controlled shop fabrication with staged dimensional inspection
  • Detailed lift plans and certified rigging supervision
  • Schedule buffers and covered work areas to protect coating quality

Results

  • Tanks installed with no dimensional rework required
  • Hydro testing passed at first attempt
  • Delivered within the agreed programme
Storage Tank Fabrication & Installation site photographStorage Tank Fabrication & Installation site photographStorage Tank Fabrication & Installation site photograph